Metro Project Indore: Two years given to the metro contractor to make the first part

Metro Project Indore: Two years given to the metro contractor to make the first part

Publish Date: | Fri, 20 Aug 2021 12: 52 PM (IST)

Amit Jaldhari, Indore, Metro Project Indore.

MR- under Indore Metro Project The deadline for construction of corridor from Bridge to Mumtazbagh has been extended to August-2023. MP Metro Rail Corporation Ltd. has issued an order in this regard. 5.10 to the contractor company Dilip Buildcon 2019 The work of this kilometer long part is about 90 crores was assigned in. This work was to be completed by March-2021, but due to differences with the consultant and the corona lockdown, the work was stalled for two years. Now the company has a challenge to complete the work in two years. However, on the assurance of getting additional time from the state government, the company started pre-construction preparations in the past and finally got additional time to work. MP Metro Rail Corporation has given extra 898 days to the contractor company. In this way, the government has given a big relief to the contractor company by giving more time than the original contract period. The new deadline will be considered as starting from March-2021 i.e. five and a half months have passed so far.

Engineer-in-Chief of Metro Rail Company Akhilesh Agarwal has said in his order that giving the company 898 extra days 16 August 2023 is given to build the elevated corridor of the metro. However, this extended time limit will be valid only if the company 10 Will withdraw all the claims made till August-21. Construction of seven stations between MR-10 Bridge to Mumtazbagh For which proposals have been sought from the construction agency now.

now waiting for the second part

MR- them) is preparing to start the work till the bridge. For this, the corporation has called for tenders and has sought proposals from the construction agencies. 10 The construction cost of this kilometer long part is one thousand crore rupees. Estimated more than Along with the construction of the corridor in the second part, nine stations will also have to be built simultaneously.